| 
          Rivergreen Developments 
          new
          rammed earth building is
          
            unusual for a 
          developer of this type, 
          they buy land, develop it using their own workforce, no 
          subcontractors, and then lease rather than sell. For us this was an 
          exciting challenge, the first UK rammed earth building by 
          non-specialist architects, engineers, surveyors and contractors.
           
          The project began with 
          soil selection, the site itself yielded 100% sand, this needed the 
          addition of clay and gravel. Testing was handled through academic 
          specialists at Bath University, lead by Professor Peter Walker. More 
          images of the
          
          rammed earth component of the build. 
          Once the mix was tested 
          and agreed we provided off site training to the Rivergreen in house 
          team. Because they all worked together and knew each others skills the 
          transfer of information on soil mixing, handling, placing and ramming, 
          as well as the assembly and stripping of the formwork was highly 
          effective. Often contractors subcontract different parts of the same 
          job to different companies or individuals which leads to information 
          delivered in training getting lost, misunderstood or ignored. In this 
          case the team was well motivated and secure in their positions.  
          The material mixing was 
          done separately from the building of the wall. This allowed them to 
          choose a time to mix outside in fine weather, place the mix in bulk 
          bags and store them on site. Bulk  |  | 
           | 
      
        | 
          bags allow storage in a 
          smaller area than in a heap, and is easier to cover and protect from 
          rain. This means the initial dig for foundations does not get in the 
          way of the job but secures the materials for when they are needed. 
          In this case the shell of 
          main building is timber and the frame and cladding were largely in 
          place when the rammed earth atrium wall was finally begun. Whatever 
          the weather outside the material was ready to use and unaffected by 
          climate. 
          We were building a large 
          job at the other end of the country when Aykley Heads started ramming. 
          With some telephone consultancy a few minor issues were quickly dealt 
          with and the contract was completed very successfully 'in house' Speaking to Peter Candler the client recently he 
          made a couple of very interesting points about the building. Initially 
          it was 80% leased to  a large public 
          sector organisation but at the end of the 7 year 
          lease with the economic situation being bad they gave up the lease. 
          Faced with an almost empty building in difficult times didn't look 
          good. But in fact the building was fully leased within six months. His 
          point was that building high spec and with materials like timber and 
          earth is a positive benefit when times are hard. Of all the empty 
          office space in the north east England it is the special buildings 
          which can sell themselves. So building with earth becomes an economic 
          virtue and necessity rather than a risk... |  |  |  |   |